Install & PTO tracker — Nguyen
SF-2025 · the stages that actually close the job — permit, utility interconnection and Permission to Operate
Permit · City of San Jose (AHJ)
ApprovedSubmitted
Jun 2
Plan check
Jun 6
Approved
Jun 9
Inspection
Jun 13
Passed
Jun 13
Utility interconnection · PG&E
Awaiting PTOApplication
Jun 3
Approved to install
Jun 8
Net-billing signed
Jun 9
PTO issued
expected Jun 20
Installation
InstalledCrew scheduled
Jun 10
Installed
Jun 12
QA & commissioning
Jun 13
Monitoring live
after PTO
All projects in delivery
| Deal | Homeowner | AHJ | Interconnection | Stage |
|---|---|---|---|---|
| SF-2025 | Nguyen Residence | Passed | Awaiting PTO | PTO |
| SF-2031 | Carlos Mendoza | Approved | Cleared | Install |
| SF-2039 | Tom & Beth Walsh | Plan check | Queued | Permitting |